NASA shuts down Maxar-led OSAM-1 satellite refueling project

A “grapple test” of the OSAM-1 spacecraft’s robotic servicing arm.

NASA

NASA is shutting down a $2 billion project to test satellite refueling in space, it announced Friday, after the agency’s auditor criticized the program’s lead contractor, Maxar, citing “poor performance.”

The space agency said in a statement that the OSAM-1 — On-orbit Servicing, Assembly, and Manufacturing 1 — project was being discontinued after nearly a decade of work.

NASA cited in its announcement “continued technical, cost, and schedule challenges, and a broader community evolution away from refueling unprepared spacecraft, which has led to a lack of a committed partner.”

The agency said in a statement to CNBC that about 450 personnel are supporting OSAM-1, but that NASA “is committed to supporting project workforce per plan through fiscal year 2024.”

“While we are disappointed by the decision to discontinue the program, we are committed to supporting NASA in pursuing potential new partnerships or alternative hardware uses as they complete the shutdown,” Maxar Space Systems spokesperson Eric Glass said in a statement to CNBC.

Maxar was taken private by private equity firm Advent International in May 2023 before being split into two businesses: Maxar Intelligence, focused on satellite imagery and analytics, and Maxar Space Systems, focused on spacecraft manufacturing.

Sign up here to receive weekly editions of CNBC’s Investing in Space newsletter.

NASA’s Goddard Space Flight Center in Maryland was leading the work on OSAM-1, with Maxar Space Systems as the project’s prime contractor under multiple deals. OSAM-1 has been in development since 2015, with the goal of docking with the U.S.-owned Landsat 7 imagery satellite in orbit, to repair and refuel the aging spacecraft to extend its life.

But OSAM-1 has fallen years behind schedule, while the program’s cost to NASA soared. In a scathing October report, NASA’s Inspector General “found that project cost increases and schedule delays were primarily due to the poor performance of Maxar,” while noting that the agency’s Goddard center has also struggled with key parts of development.

“NASA and Maxar officials acknowledged that Maxar underestimated the scope and complexity of the work, lacked full understanding of NASA technical requirements, and were deficient in necessary expertise,” NASA’s Inspector General said in its report, following a yearlong audit.

The agency’s auditor noted that OSAM-1 was likely to both “exceed its current $2.05 billion price tag and the December 2026 launch date,” which was already six years behind schedule. The report, citing Maxar representatives, noted the company was “no longer profiting from their work on OSAM-1” and, in NASA’s view, it no longer appeared “to be a high priority for Maxar in terms of the quality of its staffing.”

NASA’s cancellation of OSAM-1 comes months after Maxar delivered major segments of the spacecraft to Goddard in Maryland — but other key parts were yet to be finished.

Satellite servicing is a nascent sub-sector of the space industry that’s only recently begun to be proven out, with Northrop Grumman’s extension missions representing an early effort.

  • Related Posts

    구글 검색 누락 해결 방법은 있나요?

    구글 검색 누락 해결 구글 검색 누락 해결 방법은 있나요? 웹사이트를 운영하거나 블로그 글을 작성하는 사람이라면 한 번쯤 검색 결과에서 내 페이지가 보이지 않아 답답함을 느낀 경험이 있을 것입니다. 공들여…

    특별한 경험은 강남달토에서 가능해?

    특별한 경험은 강남달토에서 최근 사람들은 단순히 음식을 먹거나 커피를 마시는 것을 넘어, 방문 자체가 하나의 경험이 되는 공간을 찾고 있습니다. 이럴 때 자연스럽게 떠오르는 질문이 바로 “특별한 경험은 강남달토에서 가능해?”입니다.…

    Leave a Reply

    Your email address will not be published. Required fields are marked *